Tuesday, November 30, 2010

Electricians are here to finish the rough in on the new clasrooms. RTP pulled the forms on the stairs. Rain is moving in preventing work on the outside.

Monday, November 29, 2010

Electricians are here fir the rough in. Plumbers soon behind to set stacks and relocate the the hose bib. All rental equipment has been returned.



Framing up. Tarps on until roofers arrive mid-week. Walls sheeted and tyvec covering on and windows re-set. Stairs poured.

Thursday, November 18, 2010

LULL ON SITE. FRAMERS PULLING DOWN GUTTERS. WAITING FOR TRUSSES TO ROLL OFF.

Wednesday, November 17, 2010



On Monday we had to remove the Cure blankets temporarily to smooth out the wall to Spec and pull a line to square the new stem wall with the existing.

Wed
Sunny
66°F | 37°F
Thu
Partly Cloudy
64°F | 38°F
Fri
Sunny
64°F | 39°F
Sat
Sunny
68°F | 40°F


Blankets are holding despite wind and we are maintaining them wet. The rain is a big help.
Mock Wall up and ready in 3 days for inspection after mortar cures.

Monday, November 15, 2010

The first 12" fromthe top of the stem wall have been smoothed out and the brick ledge all arond has been cut to a straight line. Curing blanket are holding.

Tuesday, November 2, 2010

Forms were pulled 24 hrs after pour and the outside temp was a cool 41 deg F. We will be back-filling tomorrow and try to stay ahead of the rain.


The Weather looks bad for a couple of days.
Wed
Scattered Showers
59°F | 51°F
Thu
Showers
61°F | 40°F
Fri
Partly Cloudy
60°F | 36°F